Norton Bridge, Staffordshire RAIL

Requirement. To install a new pedestrian foot bridge to access the central platform.

A new footbridge at Norton Bridge required a topographical survey to design and arrange crane access to the site. With trains speeds over 100mph, working safely on stations and track surveys is of paramount importance. Every team member is fully trained in personal trackside safety and awareness.
click for larger picture
click for larger picture The platforms could be surveyed during daylight hours. Using the Reflectorless mode, measurements could be taken safely to the overhead power lines and the existing footbridge.
click for larger picture
click for larger picture The car park, adjacent Water Authority compound, and highway were also included. The compound was surveyed without access being necessary, thus avoiding the need to arrange a key holder. Again this was achieved using Reflectorless technology. Accuracy was maintained, and the necessary information was produced for the client.
click for larger picture
click for larger picture

200m metres of track in each direction was also required. This had to be surveyed during Engineering hours, which included two Saturday Night possessions.

We have also recently carried out a full survey of Sohlihull and Apsley Stations.Current work includes Camden and Soho Depots, Apsley and Stoke Stations.

click for larger picture
Three Spires, Coventry RAIL

Site survey and site investigation of operational Railway embankment.

Clients requirements.       
New camera locations to be established on an embankment close to railway track.
Positions of ground investigation bore hole and window samples was logged. Working together level of these locations were included on the topographical survey. click for larger picture
click for larger picture

Additional detail, such as the road bridge crossing the tracks and adjacent properties was collected quickly and efficiently with a reflectorless Total Station.

Working with Dsa Rail and WS Akins ground investigation team. click for larger picture
Rail - PinxtonRAIL
click for larger picture Date:Feb 2003.
A just one of a series of signal box surveys to submit plans for new access stairways.
Carried adjacent operational track, a survey of the building and surrounding features was recorded in co-operation with the ground investigation team.
 
click for larger picture A full site survey and photographs of the signal box and surrounding area were produced. Digital data was supplied to the client.vey of the signal box and suroundin